Roads16EH0048

CONSTRUCTION OF BAITO, POCTOY LOCAL ROAD, POCTOY, ODIONGAN, ROMBLON

CONSTRUCTION OF BAITO, POCTOY LOCAL ROAD, POCTOY, ODIONGAN, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱1,939,841.69. Status: Reported complete (DPWH). Contractor on record: TRIBU DESIGN. Figures trace to dpwh.

Romblon DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱27,233,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tulay Flood Control along Tablas Circumferential Road, Brgy. Tulay, Odiongan, Romblon
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-C-16-0019326

₱733,600.00 · FY2016

Released to 00 - Governance Commission for Government-Owned To cove (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

45 projects · ₱604.4M total · 0 flags

Other projects by this contractor

View all 45 projects →

4. Implementation

Contract Amount

₱1,939,841.69

Progress

Reported complete (DPWH)

Start Date

March 29, 2016

Target End

April 27, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.