Flood Control and Drainage17JA0026

CONSTRUCTION OF FLOOD CONTROL, LABUAN RIVER, LABUAN SECTION (INCLUDING RIGHT OF WAY ACQUISITION), ZAMBOANGA CITY 1ST DISTRICT

CONSTRUCTION OF FLOOD CONTROL, LABUAN RIVER, LABUAN SECTION (INCLUDING RIGHT OF WAY ACQUISITION), ZAMBOANGA CITY 1ST DISTRICT is a DPWH-tracked public work in Zamboanga City 2nd DEO, Region IX. Reported contract value: ₱26,909,889.65. Status: Reported complete (DPWH). Contractor on record: AEJ HARDWARE CONST & ENT. Figures trace to dpwh.

Zamboanga City 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱28,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Labuan River, Labuan Section, (Including Right of Way), Zamboanga City
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-17-0001276

₱47,493,500.00 · FY2017

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱26,909,889.65

Progress

Reported complete (DPWH)

Start Date

March 22, 2017

Target End

April 4, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.