Flood Control and Drainage24ED0070

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAGTU RIVER AT BRGY. ARANGIN, ORIENTAL MINDORO

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAGTU RIVER AT BRGY. ARANGIN, ORIENTAL MINDORO is a DPWH-tracked public work in Mindoro Oriental DEO, Region IV-B. Reported contract value: ₱144,749,987.75. Status: Reported complete (DPWH). Contractor on record: ARCONIC INC. Figures trace to dpwh.

Mindoro Oriental DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bucayao Flood Control Structure along Barangay Buhuan, Sta. 0 + 000 - Sta. 0 + 200, Calapan City, Oriental Mindoro
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Mindoro Oriental DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱144,749,987.75

Progress

Reported complete (DPWH)

Start Date

February 8, 2024

Target End

February 5, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.