Buildings and Facilities22AA0030

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY 33 CABULALAAN, BACARRA, ILOCOS NORTE

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY 33 CABULALAAN, BACARRA, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱1,979,825.14. Status: Reported complete (DPWH). Contractor on record: JCA CONST AND CONST SUPPLY 39026. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Barangay 18,17,14,13,10,9,8,7,3,2 Bacarra, Ilocos Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Ilocos Norte 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 39026

124 projects · ₱2.0B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, GUMACA-PITOGO-MULANAY-SN. NARCISO RD., K0202+745 - K0206+531, GUMACA,

Quezon 4th DEO, Region IV-A

2025₱93.4M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS, QUIRINO HIGHWAY, K0253+000 - K0254+209, GUINAYANGAN, QUEZON

Quezon 4th DEO, Region IV-A

2025₱93.1M
Reported complete (100% progress, DPWH status On-Going)
No sat.

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - MANILA NORTH ROAD - K0578+645 - K0578+700, PAGUDPUD, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2021₱92.6M
Reported complete (DPWH)

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MALING RIVER, ATIMONAN, QU

Quezon 4th DEO, Region IV-A

2025₱90.0M
Reported complete (100% progress, DPWH status On-Going)

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SEAWALL ALONG BURGOS BAY, BRGY. BOBON SECTION AND BRGY. PAAYAS SECTION, MUNICIPALITY OF BURGOS, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2022₱86.8M
Reported complete (DPWH)

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BISLAK RIVER, BRGY. DIPILAT, MUNICIPALITY OF VINTAR, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2022₱85.9M
Reported complete (DPWH)
View all 124 projects →

4. Implementation

Contract Amount

₱1,979,825.14

Progress

Reported complete (DPWH)

Start Date

February 18, 2022

Target End

May 18, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.