Water Provision and Storage23CC0598

CONSTRUCTION OF SOLAR WATER SYSTEM, PAOMBONG, BULACAN

CONSTRUCTION OF SOLAR WATER SYSTEM, PAOMBONG, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱9,796,599.60. Status: Reported complete (DPWH). Contractor on record: CHRISTINE ARA CONST SERVICES. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures along Barangay Binakod, Paombong, Bulacan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bulacan 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,796,599.60

Progress

Reported complete (DPWH)

Start Date

July 12, 2024

Target End

January 7, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.