Flood Control and Drainage20OE0088

BANK IMPROVEMENT (STEEL SHEET PILE) ALONG ESTERO DE KABULUSAN PHASE 3, MANILA CITY

BANK IMPROVEMENT (STEEL SHEET PILE) ALONG ESTERO DE KABULUSAN PHASE 3, MANILA CITY is a DPWH-tracked public work in North Manila DEO, National Capital Region. Reported contract value: ₱48,998,368.59. Status: Reported complete (DPWH). Contractor on record: DMLC BUILDERS. Figures trace to dpwh.

North Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

107 projects · ₱5.3B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF BARANGAY CALAMPINAY COASTAL ROAD (COBCOBAN SECTION), SIPOCOT, CAMARINES SUR

Camarines Sur 1st DEO, Region V

2025₱141.2M
Past target date (DPWH On-Going)

Construction of Flood Control Structure along Estero de Maypajo, Package I, Manila

CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region

2024₱113.1M
Reported complete (DPWH)

CLUSTER 9: REPAIR/REHABILITATION OF FLOOD CONTROL/DRAINAGE STRUCTURES,RAGAY, CAMARINES SUR

Camarines Sur 1st DEO, Region V

2024₱112.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT SITIO NONOK, BARANGAY MONTAÑEZA - SITIO WALO

Cebu 7th DEO, Region VII

2025₱99.8M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIESCONSTRUCTION OF REVETMENT ALONG YLANG-YLANG, SAN FRANCISCO, GEN. TRIAS, CAVITE (PHASE III)

Cavite 1st DEO, Region IV-A

2024₱99.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIESCONST OF REVETMENT ALONG RIO GRANDE RIVER RIVER, BARANGAY SANTIAGO, GEN. TRIAS, CAVITE

Cavite 1st DEO, Region IV-A

2024₱99.0M
Past target date (DPWH On-Going)
View all 107 projects →

4. Implementation

Contract Amount

₱48,998,368.59

Progress

Reported complete (DPWH)

Start Date

November 23, 2020

Target End

June 22, 2022

5. Audit