Construction of Flood Mitigation Structure22IB0073

Construction of Flood Control at Barangay San Miguel, Llorente, Eastern Samar

Construction of Flood Control at Barangay San Miguel, Llorente, Eastern Samar is a DPWH-tracked public work in LLORENTE (EASTERN SAMAR), EASTERN SAMAR, Region VIII. Reported contract value: ₱9,899,995.36. Status: Reported complete (DPWH). Contractor on record: DRAGON CONST. Figures trace to sumbong.

LLORENTE (EASTERN SAMAR), EASTERN SAMAR, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control at Barangay San Miguel, Llorente, Eastern Samar
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003173

₱326,281,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱9,899,995.36

Progress

Reported complete (DPWH)

Start Date

March 31, 2022

Target End

August 5, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.