Buildings and Facilities19JB0088

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BARANGAY HALL) BRGY. CANIBONGAN, PRES. MANUEL A. ROXAS, ZAMBOANGA DEL NORTE

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BARANGAY HALL) BRGY. CANIBONGAN, PRES. MANUEL A. ROXAS, ZAMBOANGA DEL NORTE is a DPWH-tracked public work in Zamboanga del Norte 2nd DEO, Region IX. Reported contract value: ₱199,992.21. Status: Reported complete (DPWH). Contractor on record: MORTE CONST. Figures trace to dpwh.

Zamboanga del Norte 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱199,992.21

Progress

Reported complete (DPWH)

Start Date

September 27, 2019

Target End

October 21, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.