Buildings and Facilities16CK0172

CONSTRUCTION OF MULTI PURPOSE BUILDING (EVACUATION CENTER) AT BRGY. PALUDPUD, LAPAZ, TARLAC 3RD LD

CONSTRUCTION OF MULTI PURPOSE BUILDING (EVACUATION CENTER) AT BRGY. PALUDPUD, LAPAZ, TARLAC 3RD LD is a DPWH-tracked public work in Tarlac 2nd DEO, Region III. Reported contract value: ₱7,758,491.40. Status: Reported complete (DPWH). Contractor on record: B G GIRON CONST. Figures trace to dpwh.

Tarlac 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱7,758,491.40

Progress

Reported complete (DPWH)

Start Date

February 23, 2017

Target End

July 22, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.