Flood Control and Drainage19HA0157

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF CAMAYAN RIVER FLOOD CONTROL, LORETO, CORTES, BOHOL

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF CAMAYAN RIVER FLOOD CONTROL, LORETO, CORTES, BOHOL is a DPWH-tracked public work in Bohol 1st DEO, Region VII. Reported contract value: ₱47,448,994.35. Status: Reported complete (DPWH). Contractor on record: RUDHIL CONST & ENT INC FORMERLY R 22901. Figures trace to dpwh.

Bohol 1st DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 22901

19 projects · ₱1.0B total · 0 flags

4. Implementation

Contract Amount

₱47,448,994.35

Progress

Reported complete (DPWH)

Start Date

October 11, 2019

Target End

June 5, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.