Buildings and Facilities18MH0010

CONSTRUCTION OF BARANGAY HALL CHRISTIANNUEVO, LEBAK, SULTAN KUDARAT

CONSTRUCTION OF BARANGAY HALL CHRISTIANNUEVO, LEBAK, SULTAN KUDARAT is a DPWH-tracked public work in Sultan Kudarat 2nd DEO, Region XII. Reported contract value: ₱985,547.65. Status: Reported complete (DPWH). Contractor on record: JV CONSTECH 35974. Figures trace to dpwh.

Sultan Kudarat 2nd DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱985,547.65

Progress

Reported complete (DPWH)

Start Date

March 28, 2018

Target End

May 21, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.