Buildings and Facilities20NI0077

CONSTRUCTION OF MULTI-PURPOSE BUILDING PUROK 7A, MANGAGOY, BISLIG CITY, SURIGAO DEL SUR

CONSTRUCTION OF MULTI-PURPOSE BUILDING PUROK 7A, MANGAGOY, BISLIG CITY, SURIGAO DEL SUR is a DPWH-tracked public work in Surigao del Sur 2nd DEO, Region XIII. Reported contract value: ₱974,002.39. Status: Reported complete (DPWH). Contractor on record: SMB CONST. Figures trace to dpwh.

Surigao del Sur 2nd DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱9,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/rehabilitation of flood mitigation along Bislig Bay, Cumawas, Bislig City, Surigao del Sur
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Surigao del Sur 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱974,002.39

Progress

Reported complete (DPWH)

Start Date

October 19, 2020

Target End

January 16, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.