Roads24FB0227

CLUSTER 1 - CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES

CLUSTER 1 - CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱31,322,883.20. Status: Past target date (DPWH On-Going). Contractor on record: ALXM CONSTRUCTION. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱38,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Barangay Namantao, Daraga, Albay
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Albay 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

31 projects · ₱923.3M total · 0 flags

Other projects by this contractor

No sat.

CLUSTER I - FY 2023 : ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM (1) ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROAD ALBAY WEST COAST RD - K0490+700 - K0491+140 AND K0492+000

Albay 3rd DEO, Region V

2023₱61.0M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SHORE PROTECTION STRUCTURE, BARANGAY TERRAPLIN, SAN PASCUAL, MASBATE.

Masbate 1st DEO, Region V

2025₱47.5M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF SHORE PROTECTION STRUCTURE,BARANGAY DANAO, BATUAN, MASBATE.

Masbate 1st DEO, Region V

2025₱47.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF BUSAC/GMA (ALBAY CAMARINES SUR DIVERSION ROAD) BARANGAY BUSAC TO ALBAY/CAMSUR DIVERSION ROAD, ALBAY

Albay 3rd DEO, Region V

2022₱47.2M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - SN FERNANDO NORTH RD- K0022+081- K0022+230, K0022+284 - K0023+000, K0024+000 - K0024+121, K0024+384 - K0024+434.

Masbate 1st DEO, Region V

2025₱44.5M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS- SECONDARY ROADS- SN FERNANDO NORTH RD - K0026+464 - K0026+1000, K0027+001.70 - K0027+544.10.

Masbate 1st DEO, Region V

2025₱42.8M
Past target date (DPWH On-Going)
View all 31 projects →

4. Implementation

Contract Amount

₱31,322,883.20

Progress

Past target date (DPWH On-Going)

Start Date

October 9, 2024

Target End

February 13, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.