Buildings and Facilities18CC0311

CONSTRUCTION OF TWO STOREY FOUR CLASSROOM - BAMBANG ELEMENTARY SCHOOL BULAKAN, BULACAN

CONSTRUCTION OF TWO STOREY FOUR CLASSROOM - BAMBANG ELEMENTARY SCHOOL BULAKAN, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱11,526,553.14. Status: Reported complete (DPWH). Contractor on record: ST TIMOTHY CONST CORP. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱9,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bocaue River, Bambang Section, Bocaue, Bulacan
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-18-0010470

₱28,000.00 · FY2018

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

942 projects · ₱44.1B total · 42 flags

Other projects by this contractor

No sat.

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS, MANILA NORTH RD - K0578+640 - K0578+900 R/S

Region I, Region I

2023₱390.8M
Reported complete (DPWH)
No sat.

CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS &/OR BRIDGES FR. THE NAT'L. ROAD/S LEAD. TO MAJOR/STRAT. PUBLIC BLDGS./FACILITIES-CONST. OF ROAD, BRGY. LIYANG, PILAR TO BRGY. BILOLO (PHASE 1), ORION, BATAA

Region III, Region III

2024₱305.7M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD AND CAUSEWAY FOR TOURISM ALONG AZAGRA PORT, CAJIDIOCAN, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)
No sat.

CLUSTER 12: CONST./MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, ORIENTAL MINDORO, 12.1: CONST. OF BALITE R/C, BRGY. MALAMIG SECT., STA. 0+000-STA. 0+308.60; 12.2: CONST. OF CAWACAT R/C, TABUK SECT., BULALACAO, STA.0+000-STA. 0+324.3; 1

Region IV-B, Region IV-B

2022₱289.5M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG CAJIDIOCAN PORT, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG POBLACION SAN FERNANDO, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)
View all 942 projects →

4. Implementation

Contract Amount

₱11,526,553.14

Progress

Reported complete (DPWH)

Start Date

September 16, 2018

Target End

February 27, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.