GAA 2016 MFO-116PJ0022

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ALONGBANAUE-MAYOYAO-A LISTA-ISABELA BDRY RD K0392+285-K0392+565, K0393+577-K0393+625, K0393+760-K0394+484

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ALONGBANAUE-MAYOYAO-A LISTA-ISABELA BDRY RD K0392+285-K0392+565, K0393+577-K0393+625, K0393+760-K0394+484 is a DPWH-tracked public work in Cordillera Administrative Region, Cordillera Administrative Region. Reported contract value: ₱61,941,408.35. Status: Reported complete (DPWH). Contractor on record: COLBY CONST. Figures trace to dpwh.

Cordillera Administrative Region, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

106 projects · ₱2.2B total · 0 flags

Other projects by this contractor

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDING /FACILITIES - CONSTRUCTION DABUBU PEQUEÑO FLOOD CONTROL STRUCTURE, STA. 0+000-STA.0+790, SAN AGUSTIN, ISABELA

Isabela 4th DEO, Region II

2024₱96.5M
Reported complete (100% progress, DPWH status On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF AYOD FLOOD CONTROL STRUCTURE, SECTION 1, DINAPIGUE, ISABELA

Isabela 4th DEO, Region II

2024₱96.5M
Reported complete (DPWH)

Construction of Barangay Virgoneza Flood Control Structure, Section 2, San Agustin, Isabela

SAN AGUSTIN (ISABELA), ISABELA, Region II

2023₱96.5M
Reported complete (DPWH)

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEM - CONSTRUCTION OF BARANGAY SINAOANGAN SUR FLOOD CONTROL STRUCTURE, SECTIO

Isabela 4th DEO, Region II

2023₱96.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDING /FACILITIES - CONSTRUCTION OF PAYAC FLOOD CONTROL STRUCTURE, STA. 0+000 - STA. 0+700, JONES, ISABELA

Isabela 4th DEO, Region II

2024₱96.0M
Past target date (DPWH On-Going)
No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ALFONSO LISTA - AURORA BDRY. ROAD - K0452 + 392 - K0453 + 849, KO453 + 950 - KO454 + 993

Ifugao 2nd DEO, Cordillera Administrative Region

2017₱95.9M
Reported complete (DPWH)
View all 106 projects →

4. Implementation

Contract Amount

₱61,941,408.35

Progress

Reported complete (DPWH)

Start Date

April 4, 2016

Target End

August 3, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.