CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, MANGIMA-AGUSAN CANYON BYPASS ROAD, BUKIDNON

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, MANGIMA-AGUSAN CANYON BYPASS ROAD, BUKIDNON is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱84,946,892.79. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: M MONTESCLAROS ENT INC 6506. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱84,946,892.79

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

April 18, 2024

Target End

May 27, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.