Bridges24I00294

BRIDGE - RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - HIBUGA BR. (B00069LT) ALONG DAANG MAHARLIKA (LT), LEYTE 2ND LD

BRIDGE - RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - HIBUGA BR. (B00069LT) ALONG DAANG MAHARLIKA (LT), LEYTE 2ND LD is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱5,302,424.11. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: FAIRCHILD BUILDERS. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱5,302,424.11

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

October 7, 2024

Target End

February 3, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.