Flood Control and Drainage21FH0056

LOCAL PROGRAM-FLOOD CONTROL AND DRAINAGE-FLOOD CONTROL STRUCTURES/FACILITIES-LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-CONSTRUCTION OF RIVER FLOOD CONTROL STRUCTURE, BARANGAY MABINI PROPER, CARAMORAN, CATANDUANES

LOCAL PROGRAM-FLOOD CONTROL AND DRAINAGE-FLOOD CONTROL STRUCTURES/FACILITIES-LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-CONSTRUCTION OF RIVER FLOOD CONTROL STRUCTURE, BARANGAY MABINI PROPER, CARAMORAN, CATANDUANES is a DPWH-tracked public work in Catanduanes DEO, Region V. Reported contract value: ₱14,698,084.77. Status: Reported complete (DPWH). Contractor on record: BICOL GOLDROCK CONST CORP. Figures trace to dpwh.

Catanduanes DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of River Flood Control Structure, Barangay Mabini Proper, Caramoran, Catanduanes
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Catanduanes DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

253 projects · ₱14.5B total · 12 flags

Other projects by this contractor

No sat.

CLUSTER I-ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-I-A: REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS-CATANDUANES CIR RD-K0028+000-K0028+647, K0028+788-K0029+000, K

Catanduanes DEO, Region V

2025₱218.7M
Ongoing (DPWH-reported)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF BICOL RIVER FLOOD MITIGATION STR

Region V, Region V

2024₱148.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS(TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)PASACAO-BALATAN TOURISM COASTAL HIGHWAY, PASACAO, CAMARINES SUR, PACKAGE 3, CAMARINES SUR(2N

Region V, Region V

2022₱144.8M
Reported complete (DPWH)
No sat.

CSSP: CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN) - SAN ISIDRO-BAHAO ROAD LEADING TO BAHAO PORT, LIBMANAN, CAMARINES SUR, PACKAGE C

Camarines Sur 2nd DEO, Region V

2025₱143.3M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF ROAD, TAGBAC, RAGAY, CAMARINES SUR

Camarines Sur 1st DEO, Region V

2025₱139.6M
Past target date (DPWH On-Going)

OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG LIBMANAN RIVER (RIGHT SIDE) WITHIN BICOL RIVER BASIN, BARANGAY MA

Camarines Sur 2nd DEO, Region V

2024₱135.1M
Reported complete (DPWH)
View all 253 projects →

4. Implementation

Contract Amount

₱14,698,084.77

Progress

Reported complete (DPWH)

Start Date

March 25, 2021

Target End

May 2, 2022

5. Audit