Flood Control and Drainage24HO0152

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF REVETMENT WALL AT SITIO UPPER TALAYONG (LEFT SIDE)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF REVETMENT WALL AT SITIO UPPER TALAYONG (LEFT SIDE) is a DPWH-tracked public work in Cebu 7th DEO, Region VII. Reported contract value: ₱94,109,912.98. Status: Past target date (DPWH On-Going). Contractor on record: JCM AMEG BUILDERS CORP FORMERLY: AMEG CONST. Figures trace to dpwh.

Cebu 7th DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment Wall along Talaba River Flood Control, Barangay Canduling, Ronda, Cebu
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Cebu 7th DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

27 projects · ₱1.5B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT PUROK ACACIA (LEFT SIDE), BARANGAY LIBOO, RO

Cebu 7th DEO, Region VII

2025₱99.8M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF COASTAL ROAD WITH STORM SURGE PROTECTION, BUHATAN-SALVACION, SANTO DOMINGO, ALBAY

Albay 1st DEO, Region V

2022₱95.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT PUROK KALUBIHAN I, BARANGAY LIBOO, RONDA, CE

Cebu 7th DEO, Region VII

2025₱95.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF REVETMENT WALL, BARANGAY BUTONG TO BARANGAY TUPAS, RONDA,

Cebu 7th DEO, Region VII

2025₱95.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTSALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES,CONSTRUCTION OF REVETMENT WALL AT SITIO UPPER TALAYONG, BRGY. TUPAS, RONDA, CE

Cebu 7th DEO, Region VII

2023₱94.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BRGY. TUPAS

Cebu 7th DEO, Region VII

2024₱94.1M
Past target date (DPWH On-Going)
View all 27 projects →

4. Implementation

Contract Amount

₱94,109,912.98

Progress

Past target date (DPWH On-Going)

Start Date

January 13, 2025

Target End

November 15, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.