Construction of Flood Mitigation Structure21JF0011

Construction of Flood Control Structure along Lanao-Pagadian-Zamboanga City Road, Buluan River (Phase II) (Upstream), Zamboanga Sibugay

Construction of Flood Control Structure along Lanao-Pagadian-Zamboanga City Road, Buluan River (Phase II) (Upstream), Zamboanga Sibugay is a DPWH-tracked public work in ZAMBOANGA SIBUGAY, Region IX. Reported contract value: ₱42,112,247.18. Status: Reported complete (DPWH). Contractor on record: JAYKRIS ENT & CONST FORMERLY: JAYKRIS ENT. Figures trace to sumbong.

ZAMBOANGA SIBUGAY, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱44,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Lanao-Pagadian-Zamboanga City Road, Buluan River (Phase II) (Upstream), Zamboanga Sibugay
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIX-21-0000753

₱855,557.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIX-21-0009137

₱832,315.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIX-21-0000754

₱77,952.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014141

₱35,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIX-21-0008563

₱44,672.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIX-21-0008564

₱4,455.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIX-21-0009138

₱71,605.00 · FY2021

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱42,112,247.18

Progress

Reported complete (DPWH)

Start Date

February 17, 2021

Target End

October 9, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.