Roads19MH0089

CONCRETING OF ROAD FROM NRJ TO SITIO SEWAL LEADING TO LAGBASAN CAVE PASSING THRU BURIAL CAVE BRGY. KUDEN, SEN. NINOY AQUINO, SULTAN KUDARAT

CONCRETING OF ROAD FROM NRJ TO SITIO SEWAL LEADING TO LAGBASAN CAVE PASSING THRU BURIAL CAVE BRGY. KUDEN, SEN. NINOY AQUINO, SULTAN KUDARAT is a DPWH-tracked public work in Sultan Kudarat 2nd DEO, Region XII. Reported contract value: ₱44,879,100.00. Status: Reported complete (DPWH). Contractor on record: LEGACY CONST CORP FORMERLY: LEGACY CONST. Figures trace to dpwh.

Sultan Kudarat 2nd DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVII-19-0021904

₱9,500,000.00 · FY2019

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1,112 projects · ₱59.5B total · 113 flags

Other projects by this contractor

No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD AND CAUSEWAY, BRGY. CAMBAJAO-BRGY. ALIBAGON, CAJIDIOCAN, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2024₱297.0M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG CARMEN PORT, SAN AGUSTIN, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG SAN JOSE PORT, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Past target date (DPWH On-Going)

Construction of Dubduban Flood Control Structure, San Agustin, Tablas Island Romblon

ALCANTARA (ROMBLON), ROMBLON, Region IV-B

2023₱289.5M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MONGPONG, BRGY. STA. LUCIA, SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2024₱289.5M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. CENTRAL-BRGY. SAN AGUSTIN, STA. 000+240-STA. 000+735.5 (LEFT SIDE), SAN JOSE, OCC. MIND

Region IV-B, Region IV-B

2025₱284.2M
Past target date (DPWH On-Going)
View all 1,112 projects →

4. Implementation

Contract Amount

₱44,879,100.00

Progress

Reported complete (DPWH)

Start Date

July 31, 2019

Target End

December 24, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.