Construction of Revetment22KB0073

Construction of Revetment, Downstream and Upstream of San Miguel Bridge (B01432MN) along Maramag-Maradugao Road, Bukidnon

Construction of Revetment, Downstream and Upstream of San Miguel Bridge (B01432MN) along Maramag-Maradugao Road, Bukidnon is a DPWH-tracked public work in MARAMAG (BUKIDNON), BUKIDNON, Region X. Reported contract value: ₱67,550,000.00. Status: Reported complete (DPWH). Contractor on record: PYRAMID CONSOLIDATED BUILDERS & GEN MDSE. Figures trace to sumbong.

MARAMAG (BUKIDNON), BUKIDNON, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along CDO City Dominorog Camp Kibaritan Rd (Upstream and Downstream of Tal-uban Bridge) Phase 3, Talakag, Bukidnon
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003123

₱718,520,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0010240

₱100,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0005381

₱5,751,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003061

₱3,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0005382

₱572,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱67,550,000.00

Progress

Reported complete (DPWH)

Start Date

February 24, 2022

Target End

January 19, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.