Flood Control and Drainage25PI0040

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CHICO RIVER ALAB-BALILI SECTION, STA. 39+415 - STA. 39+507 (LS), BONTOC, MOUNTAIN PROVINCE

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CHICO RIVER ALAB-BALILI SECTION, STA. 39+415 - STA. 39+507 (LS), BONTOC, MOUNTAIN PROVINCE is a DPWH-tracked public work in Mountain Province 1st DEO, Cordillera Administrative Region. Reported contract value: ₱9,701,999.50. Status: Past target date (DPWH On-Going). Contractor on record: ALPHA SIX CONST. Figures trace to dpwh.

Mountain Province 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Chico River, Alab-Balili Section, Sta.39 + 415 - Sta. 39 + 507 (LS) Bontoc, Mountain Province
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Mountain Province 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

22 projects · ₱170.1M total · 0 flags

Other projects by this contractor

View all 22 projects →

4. Implementation

Contract Amount

₱9,701,999.50

Progress

Past target date (DPWH On-Going)

Start Date

April 13, 2025

Target End

July 14, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.