Roads25FN0026

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - BAAO-IRIGA CITY-NABUA RD - K0474 + 230 - K0474 + 885

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - BAAO-IRIGA CITY-NABUA RD - K0474 + 230 - K0474 + 885 is a DPWH-tracked public work in Camarines Sur 5th DEO, Region V. Reported contract value: ₱31,170,860.00. Status: Past target date (DPWH On-Going). Contractor on record: DMLC BUILDERS. Figures trace to dpwh.

Camarines Sur 5th DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱8,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Zone 2 and Zone 4, Barangay Dangla, Garchitorena, Camarines Sur
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Camarines Sur 5th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

Probable match · 87%

Repair/Maintenance of River Revetment 1, Sinagtala

₱28,226,250.03 · DMLC BUILDERS

Contractor

B

107 projects · ₱5.3B total · 1 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF BARANGAY CALAMPINAY COASTAL ROAD (COBCOBAN SECTION), SIPOCOT, CAMARINES SUR

Camarines Sur 1st DEO, Region V

2025₱141.2M
Past target date (DPWH On-Going)

Construction of Flood Control Structure along Estero de Maypajo, Package I, Manila

CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region

2024₱113.1M
Reported complete (DPWH)

CLUSTER 9: REPAIR/REHABILITATION OF FLOOD CONTROL/DRAINAGE STRUCTURES,RAGAY, CAMARINES SUR

Camarines Sur 1st DEO, Region V

2024₱112.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT SITIO NONOK, BARANGAY MONTAÑEZA - SITIO WALO

Cebu 7th DEO, Region VII

2025₱99.8M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIESCONSTRUCTION OF REVETMENT ALONG YLANG-YLANG, SAN FRANCISCO, GEN. TRIAS, CAVITE (PHASE III)

Cavite 1st DEO, Region IV-A

2024₱99.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIESCONST OF REVETMENT ALONG RIO GRANDE RIVER RIVER, BARANGAY SANTIAGO, GEN. TRIAS, CAVITE

Cavite 1st DEO, Region IV-A

2024₱99.0M
Past target date (DPWH On-Going)
View all 107 projects →

4. Implementation

Contract Amount

₱31,170,860.00

Progress

Past target date (DPWH On-Going)

Start Date

June 10, 2025

Target End

January 23, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.