Construction of Flood Mitigation Structure24DF0156

Construction of Revetment along Julian River, Brgy. Kalsadang Bago, Imus City, Cavite (Phase 2)

Construction of Revetment along Julian River, Brgy. Kalsadang Bago, Imus City, Cavite (Phase 2) is a DPWH-tracked public work in IMUS CITY (CAVITE), CAVITE, Region IV-A. Reported contract value: ₱99,000,000.00. Status: Reported complete (DPWH). Contractor on record: MOTIONTRADE DEVELOPMENT CORP / OMNICON BUILDERS. Figures trace to sumbong.

IMUS CITY (CAVITE), CAVITE, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Kay - Akle RIS Water Management Flood Control Project of Kay - Akle River, Maragondon, Cavite
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Cavite 1st District Engineering Office · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱99,000,000.00

Progress

Reported complete (DPWH)

Start Date

March 20, 2024

Target End

December 21, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.