Buildings and Facilities19BC0308

LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING, CALOG SUR ELMENTARY SCHOOL, BRGY. CALOG SUR, ABULUG, CAGAYAN

LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING, CALOG SUR ELMENTARY SCHOOL, BRGY. CALOG SUR, ABULUG, CAGAYAN is a DPWH-tracked public work in Cagayan 2nd DEO, Region II. Reported contract value: ₱982,845.92. Status: Reported complete (DPWH). Contractor on record: J G YACAS CONST SUPPLY AND EQUIPMENT RENTAL. Figures trace to dpwh.

Cagayan 2nd DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

110 projects · ₱1.7B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF MULTI-PURPOSE BUILDING (GOVERNMENT CENTER PACKAGE 4), LIBERTAD, ABULUG, CAGAYAN

Cagayan 2nd DEO, Region II

2024₱99.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF DUGO FLOOD CONTROL ALONG ABULU

Cagayan 2nd DEO, Region II

2025₱96.3M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF LIBERTAD FLOOD CONTROL STRUCTUR

Cagayan 2nd DEO, Region II

2025₱96.3M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF DUGO FLOOD CONTROL CONTROL STR

Cagayan 2nd DEO, Region II

2025₱96.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF ABULUG RIVER REVETMENT 9 ALO

Cagayan 2nd DEO, Region II

2025₱96.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF CAGAYAN RIVER REVETMENT 5 AL

Cagayan 2nd DEO, Region II

2025₱96.3M
Past target date (DPWH On-Going)
View all 110 projects →

4. Implementation

Contract Amount

₱982,845.92

Progress

Reported complete (DPWH)

Start Date

August 29, 2019

Target End

January 22, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.