Flood Control and Drainage25CD0145

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG STO. CRISTO RIVER, STA. 10+600 STA.10+750, CITY OF SAN JOSE DEL MONTE, BULACAN

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG STO. CRISTO RIVER, STA. 10+600 STA.10+750, CITY OF SAN JOSE DEL MONTE, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱93,583,808.98. Status: Past target date (DPWH On-Going). Contractor on record: LAMASIA BUILDERS AND SUPPLY CORP. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Angat River, Poblacion Section, Sta.14+834 - Sta. 14+922, Norzagaray, Bulacan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bulacan 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱93,583,808.98

Progress

Past target date (DPWH On-Going)

Start Date

April 2, 2025

Target End

January 20, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.