Buildings and Facilities18OG0035

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. LAGING HANDA, QUEZON CITY

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. LAGING HANDA, QUEZON CITY is a DPWH-tracked public work in Quezon City 2nd DEO, National Capital Region. Reported contract value: ₱1,970,001.40. Status: Reported complete (DPWH). Contractor on record: CZERJ CONST. Figures trace to dpwh.

Quezon City 2nd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,970,001.40

Progress

Reported complete (DPWH)

Start Date

March 16, 2018

Target End

June 25, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.