Bridges22HC0061

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND /OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF THE TALIBON-BIEN UNIDO BRIDGE, BOHOL

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND /OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF THE TALIBON-BIEN UNIDO BRIDGE, BOHOL is a DPWH-tracked public work in Bohol 2nd DEO, Region VII. Reported contract value: ₱48,553,000.00. Status: Reported complete (DPWH). Contractor on record: LABB CONST DEVELOPMENT INC FORMERLY: LABB CONST 13524. Figures trace to dpwh.

Bohol 2nd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Capayas Flood Control, Ubay, Bohol
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Bohol 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 13524

103 projects · ₱4.3B total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM, CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS , LOCAL ROADS AND BRIDGES, LOCAL ROADS, CONSTRUCTION OF ROAD, JCT. (LIR) SAN MIGUEL-BAYONGAN-BULILIS-MABUHAY, UBAY, BOHOL, STA.0+000-STA.7+1

Region VII, Region VII

2021₱231.6M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - IMPROVEMENT/WIDENING OF NATIONAL ROADS - PRIMARY ROADS - OTHER PRIMARY ROADS ORMOC-BAYBAY-SOUTHERN LEYTE BOUNDARY ROAD - K1043+120-K1043+325, K1043+341-K1043+809, K1043+838-K1044+870, K1046+835-K1047+147, K1047+824-K1048+091, K1048+1

Leyte 5th DEO, Region VIII

2017₱144.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF DRAINAGE STRUCTURE, JCT. TAGBILARAN NORTH ROAD K0002 + 170 AND PEÑAFLOR STREET LEADING TO OUTFALL WITH INTEGRATED WASTE WATER TREATMENT, BARANGAY COGON, BARANG

Bohol 1st DEO, Region VII

2025₱144.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, JCT. (LIR) SAN MIGU

Region VII, Region VII

2022₱125.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-CONSTRUCTION OF BY-PASS/DIVERSION ROAD, KILIM-SITIO TIPAY ROAD JUNCTION ORMOC BAYBAY SOUTHERN LEYTE BDRY. ROAD TO BUENAVISTA ...(PACKAGE 3), LEYTE 5TH LD

Region VIII, Region VIII

2021₱114.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROADS LEADING TO TALIBON-BIE

Bohol 2nd DEO, Region VII

2023₱96.5M
Reported complete (DPWH)
View all 103 projects →

4. Implementation

Contract Amount

₱48,553,000.00

Progress

Reported complete (DPWH)

Start Date

April 6, 2022

Target End

March 12, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.