Buildings and Facilities20HK0013

LOCALLY FUNDED PROJECTS-BUILDINGS AND OTHER STRUCTURES-MULTIPURPOSE/FACILITIES-LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. DANSULAN, BAIS, NEGROS ORIENTAL

LOCALLY FUNDED PROJECTS-BUILDINGS AND OTHER STRUCTURES-MULTIPURPOSE/FACILITIES-LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. DANSULAN, BAIS, NEGROS ORIENTAL is a DPWH-tracked public work in Negros Oriental 2nd DEO, Negros Island Region. Reported contract value: ₱1,958,880.00. Status: Reported complete (DPWH). Contractor on record: R E SINGSON CONST AND DEVELOPMENT INC FORMERLY: R E SINGSON CONST. Figures trace to dpwh.

Negros Oriental 2nd DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Brgy. San Jose, Manjuyod, Negros Oriental
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Negros Oriental 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction Project

₱1,958,880.00 · R.E. SINGSON CONSTRUCTION

Contractor

Other projects by this contractor

No sat.

ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: PRIMARY ROADS - ROAD WIDENING AT SPECIFIC LOCATIONS ALONG DUMAGUETE NORTH ROAD (DUMAGUETE - JCT BAIS - KABANKALAN) K0018+900 - K0020+399, AMLAM, NEGROS ORIENTAL

Negros Oriental 2nd DEO, Negros Island Region

2022₱60.3M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROAD-PRIMARY ROADS-DUMAGUETE NORTH RD (DUMAGUETE-JCT BAIS-KABANKALAN) K0035+046-K0036+500

Negros Oriental 2nd DEO, Negros Island Region

2024₱46.1M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM -ROAD WIDENING - PRIMARY ROADS-DUMAGUETE NORTH RD (DUMAGUETE-JCT BAIS-KABANKALAN)- K0003+491-K0004+000

Negros Oriental 2nd DEO, Negros Island Region

2025₱32.1M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM: ROAD WIDENING-PRIMARY ROADS-DUMAGUETE NORTH RD (DUMAGUETE-JCT-BAIS-KABANKALAN)-K0021+973-K0022+538, NEGROS ORIENTAL

Negros Oriental 2nd DEO, Negros Island Region

2024₱31.4M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING(SPORTS COMPLEX),MABINAY, NEGROS ORIENTAL

Negros Oriental 2nd DEO, Negros Island Region

2024₱29.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP) - ACCESS ROAD LEADING TO BUGSOK FALLS, MABINAY, NEGROS ORIENTAL

Negros Oriental 2nd DEO, Negros Island Region

2023₱29.4M
Reported complete (DPWH)
View all 88 projects →

4. Implementation

Contract Amount

₱1,958,880.00

Progress

Reported complete (DPWH)

Start Date

January 31, 2020

Target End

May 9, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.