Buildings and Facilities18AA0050

REHAB OF MPB BGRY PANINAAN BACARRA, I.N.

REHAB OF MPB BGRY PANINAAN BACARRA, I.N. is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱881,124.58. Status: Reported complete (DPWH). Contractor on record: ZEDIK BUILDERS. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Dredging of Bacarra River, Bacarra, Ilocos Norte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Agency-level releases for FY2018, not tied to this contract

Ilocos Norte 1st DEO · SARO 1,489 (₱126,676,811,675.00) · NCA 1,617 (₱426,584,627,343.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱881,124.58

Progress

Reported complete (DPWH)

Start Date

February 12, 2018

Target End

April 12, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.