Roads20HC0008

001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- NETWORK DEVELOPMENT PROGRAM- ROAD WIDENING - SECONDARY ROADS - TAGBILARAN NORTH RD (TAGBILARAN-JETAFE SECT)K0059+199 - K0060+262, K0060+497 - K0060+747, CLARIN, BOHOL

001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- NETWORK DEVELOPMENT PROGRAM- ROAD WIDENING - SECONDARY ROADS - TAGBILARAN NORTH RD (TAGBILARAN-JETAFE SECT)K0059+199 - K0060+262, K0060+497 - K0060+747, CLARIN, BOHOL is a DPWH-tracked public work in Bohol 2nd DEO, Region VII. Reported contract value: ₱36,500,000.00. Status: Reported complete (DPWH). Contractor on record: LABB CONST DEVELOPMENT INC FORMERLY: LABB CONST. Figures trace to dpwh.

Bohol 2nd DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

111 projects · ₱4.8B total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM, CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS , LOCAL ROADS AND BRIDGES, LOCAL ROADS, CONSTRUCTION OF ROAD, JCT. (LIR) SAN MIGUEL-BAYONGAN-BULILIS-MABUHAY, UBAY, BOHOL, STA.0+000-STA.7+1

Region VII, Region VII

2021₱231.6M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - IMPROVEMENT/WIDENING OF NATIONAL ROADS - PRIMARY ROADS - OTHER PRIMARY ROADS ORMOC-BAYBAY-SOUTHERN LEYTE BOUNDARY ROAD - K1043+120-K1043+325, K1043+341-K1043+809, K1043+838-K1044+870, K1046+835-K1047+147, K1047+824-K1048+091, K1048+1

Leyte 5th DEO, Region VIII

2017₱144.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF DRAINAGE STRUCTURE, JCT. TAGBILARAN NORTH ROAD K0002 + 170 AND PEÑAFLOR STREET LEADING TO OUTFALL WITH INTEGRATED WASTE WATER TREATMENT, BARANGAY COGON, BARANG

Bohol 1st DEO, Region VII

2025₱144.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, JCT. (LIR) SAN MIGU

Region VII, Region VII

2022₱125.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-CONSTRUCTION OF BY-PASS/DIVERSION ROAD, KILIM-SITIO TIPAY ROAD JUNCTION ORMOC BAYBAY SOUTHERN LEYTE BDRY. ROAD TO BUENAVISTA ...(PACKAGE 3), LEYTE 5TH LD

Region VIII, Region VIII

2021₱114.7M
Reported complete (DPWH)

Construction of Flood Mitigation Structure at Malitbog River Phase 2, Dagohoy, Bohol

DAGOHOY (BOHOL), BOHOL, Region VII

2022₱96.5M
Reported complete (DPWH)
View all 111 projects →

4. Implementation

Contract Amount

₱36,500,000.00

Progress

Reported complete (DPWH)

Start Date

December 10, 2020

Target End

June 27, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.