Construction of Revetment22AI0107

Construction of Flood Control Structure along Lagasit River, Brgy. Namagbagan, Sta. Maria, Pangasinan

Construction of Flood Control Structure along Lagasit River, Brgy. Namagbagan, Sta. Maria, Pangasinan is a DPWH-tracked public work in SANTA MARIA (PANGASINAN), PANGASINAN, Region I. Reported contract value: ₱28,517,854.91. Status: Reported complete (DPWH). Contractor on record: R A MATIAS CONST AND DEVELOPERS INC FORMERLY : R A MATIAS CONST AND DEVELOPERS. Figures trace to sumbong.

SANTA MARIA (PANGASINAN), PANGASINAN, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Lagasit River, Brgy. Namagbagan, Sta. Maria, Pangasinan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002947

₱753,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003035

₱40,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003014

₱10,000,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱28,517,854.91

Progress

Reported complete (DPWH)

Start Date

February 24, 2022

Target End

August 12, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.