Buildings and Facilities22NF0143

CONSTRUCTION (COMPLETION) OF 2STY4CL, OGUING NAVARRO MEMORIAL NATIONAL HIGH SCHOOL, DEL CARMEN, SURIGAO DEL NORTE

CONSTRUCTION (COMPLETION) OF 2STY4CL, OGUING NAVARRO MEMORIAL NATIONAL HIGH SCHOOL, DEL CARMEN, SURIGAO DEL NORTE is a DPWH-tracked public work in Surigao del Norte 1st DEO, Region XIII. Reported contract value: ₱2,990,007.84. Status: Reported complete (DPWH). Contractor on record: SEVERS CONST. Figures trace to dpwh.

Surigao del Norte 1st DEO, Region XIII
Region: Region XIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Dapja-Katunggan Flood Control Structure, Tagana-an, Surigao del Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Surigao del Norte 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

63 projects · ₱828.0M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING (LGU HOTEL) BRGY. 6, DAPA, SURIGAO DEL NORTE

Surigao del Norte 1st DEO, Region XIII

2023₱79.2M
Reported complete (DPWH)
No sat.

CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING (SIARGAO CLIMATE FIELD SCHOOL OF SURIGAO DEL NORTE STATE UNIVERSITY) - DEL CARMEN CAMPUS, BRGY. SAN JOSE, DEL CARMEN, SIARGAO ISLAND, SURIGAO DEL NORTE

Surigao del Norte 1st DEO, Region XIII

2025₱49.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT DINAS RIVER ALONG ZAMBOANGA DEL SUR COASTAL RD (S01168MN) AND GUINICULALAY BR., BARANGAY OLD MIRAPAO, DINAS, ZAMBOANGA DEL SUR

Zamboanga del Sur 2nd DEO, Region IX

2025₱48.9M
Past target date (DPWH On-Going)
No sat.

ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY POBLACION - BARANGAY PANUBIGAN - BARANGAY LOWER PANIKI-AN - BARANGAY PUNTA FLECHA - BARANGAY LIMBAYAN, PITOGO, ZD

Zamboanga del Sur 2nd DEO, Region IX

2025₱48.9M
Past target date (DPWH On-Going)
No sat.

ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY LEGARDA - BARANGAY LEGARDA 3 - BARANGAY IGNACIO GARRATA, DINAS, ZAMBOANGA DEL SUR

Zamboanga del Sur 2nd DEO, Region IX

2025₱40.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, DAPA, SURIGAO DEL NORTE (PHASE 2)

Surigao del Norte 1st DEO, Region XIII

2024₱39.6M
Reported complete (DPWH)
View all 63 projects →

4. Implementation

Contract Amount

₱2,990,007.84

Progress

Reported complete (DPWH)

Start Date

December 30, 2022

Target End

March 29, 2023

5. Audit