Roads25KI0043

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY PUNTOD-BAR

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY PUNTOD-BAR is a DPWH-tracked public work in Misamis Occidental 1st DEO, Region X. Reported contract value: ₱19,480,129.90. Status: Past target date (DPWH On-Going). Contractor on record: ANIMAS BROS CONST CORP FORMERLY: ANIMAS BROS CONST 35002. Figures trace to dpwh.

Misamis Occidental 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Pines River, Aloran and Oroquieta City, Misamis Occidental
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Misamis Occidental 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 35002

35 projects · ₱1.1B total · 0 flags

4. Implementation

Contract Amount

₱19,480,129.90

Progress

Past target date (DPWH On-Going)

Start Date

June 8, 2025

Target End

October 20, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.