Buildings and Facilities23C00320

CONSTRUCTION OF 1STY2CL, SAMPALOC INTEGRATED SCHOOL, MORONG, BATAAN

CONSTRUCTION OF 1STY2CL, SAMPALOC INTEGRATED SCHOOL, MORONG, BATAAN is a DPWH-tracked public work in Region III, Region III. Reported contract value: ₱5,292,000.00. Status: Reported complete (DPWH). Contractor on record: R C S CONST. Figures trace to dpwh.

Region III, Region III
Region: Region III

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱5,292,000.00

Progress

Reported complete (DPWH)

Start Date

November 23, 2023

Target End

April 20, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.