Buildings and Facilities18LA0055

CONSTRUCTION OF MPB (DAY CARE CENTER), SITIO TOTOY, BRGY. HAGUIMITAN, MONKAYO, COMPOSTELA VALLEY PROVINCE

CONSTRUCTION OF MPB (DAY CARE CENTER), SITIO TOTOY, BRGY. HAGUIMITAN, MONKAYO, COMPOSTELA VALLEY PROVINCE is a DPWH-tracked public work in Davao de Oro 1st DEO, Region XI. Reported contract value: ₱2,058,701.48. Status: Reported complete (DPWH). Contractor on record: AB APONESTO CONST PARTS AND SUPPLY INC 22998. Figures trace to dpwh.

Davao de Oro 1st DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,058,701.48

Progress

Reported complete (DPWH)

Start Date

February 28, 2018

Target End

June 27, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.