Flood Control and Drainage17IB0039

REHABILITATION AND EXTENSION OF FLOOD CONTROL PROJECT ALONG BOLUSAO RIVER, BRGY. 6. POBLACION, BRGY. TAGUITE AND BRGY. BOLUSAO, LAWAAN, EASTERN SAMAR LONE DISTRICT

REHABILITATION AND EXTENSION OF FLOOD CONTROL PROJECT ALONG BOLUSAO RIVER, BRGY. 6. POBLACION, BRGY. TAGUITE AND BRGY. BOLUSAO, LAWAAN, EASTERN SAMAR LONE DISTRICT is a DPWH-tracked public work in Eastern Samar DEO, Region VIII. Reported contract value: ₱48,999,926.08. Status: Reported complete (DPWH). Contractor on record: 888 ACY ENT. Figures trace to dpwh.

Eastern Samar DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 96%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation and Extension of Flood Control Project along Bolusao River, Brgy. 6. Poblacion, Brgy. Taguite and Brgy. Bolusao, Lawaan, Eastern Samar
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-17-0013214

₱179,017.00 · FY2017

Released to Mulapula National Rel High School to (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

292 projects · ₱9.1B total · 5 flags

4. Implementation

Contract Amount

₱48,999,926.08

Progress

Reported complete (DPWH)

Start Date

March 13, 2017

Target End

December 29, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.