Roads23BG0062

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES-CONST. OF VILLA CARMEN IRRIGATION SERVICE RD, RAMON,

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES-CONST. OF VILLA CARMEN IRRIGATION SERVICE RD, RAMON, is a DPWH-tracked public work in Isabela 3rd DEO, Region II. Reported contract value: ₱4,825,093.62. Status: Reported complete (DPWH). Contractor on record: A COLOMA CONST. Figures trace to dpwh.

Isabela 3rd DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Cagayan River Flood Control Project, Barangay Villa Domingo, Angadanan, Isabela
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Isabela 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

10 projects · ₱149.6M total · 0 flags

Other projects by this contractor

No sat.

OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SIFFU RIVER FLOOD CONTROL STRUCTURE, PHASE 3, SAN ANTONINO SECTION, BURGOS, ISABELA

Isabela 2nd DEO, Region II

2025₱96.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP), ACCESS ROAD LEADING TO BANTAY LAKAY IN CALAOCAN, CABARROGUIS, QUIRINO

Quirino DEO, Region II

2024₱14.3M
Reported complete (DPWH)
No sat.

CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY VILLA FUERTE, SAN MATEO, ISABELA (PHASE 2)

Isabela 3rd DEO, Region II

2024₱4.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES-CONCRETING OF ROAD, BARANGAY VILLAFUERTE,SAN MATEO, ISABELA (PHASE 1

Isabela 3rd DEO, Region II

2024₱4.9M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS FACILITIES - CONSTRUCTION OF DINGASAN ROAD, BARANGAY DINGASAN, CABARROGUIS, QUIRINO

Quirino DEO, Region II

2025₱4.9M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES -CONSTRUCTION OF ROAD, BARANGAY SAN ROQUE, SAN MATEO, ISABELA

Isabela 3rd DEO, Region II

2024₱4.9M
Reported complete (DPWH)
View all 10 projects →

4. Implementation

Contract Amount

₱4,825,093.62

Progress

Reported complete (DPWH)

Start Date

February 24, 2023

Target End

March 30, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.