Roads25HI0072

CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, PUROK CAMATES TO PUROK SIBUYAS, BARANGAY CALERO, LIL

CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, PUROK CAMATES TO PUROK SIBUYAS, BARANGAY CALERO, LIL is a DPWH-tracked public work in Cebu 5th DEO, Region VII. Reported contract value: ₱19,206,709.66. Status: Past target date (DPWH On-Going). Contractor on record: WQC DESIGN AND CONST. Figures trace to dpwh.

Cebu 5th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 78%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Guadalupe, Cebu City, Cebu
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cebu 5th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱19,206,709.66

Progress

Past target date (DPWH On-Going)

Start Date

August 8, 2025

Target End

December 5, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.