Water Provision and Storage23HN0205

CSSP : CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY POBLACION, CORDOVA, CEBU

CSSP : CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY POBLACION, CORDOVA, CEBU is a DPWH-tracked public work in Cebu 6th DEO, Region VII. Reported contract value: ₱9,775,000.00. Status: Reported complete (DPWH). Contractor on record: J810 CONST AND DEVELOPMENT CORP FORMERLY: J810 CONST CORP. Figures trace to dpwh.

Cebu 6th DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱8,238,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Cansaga River, Barangay Danglag, Consolacion, Cebu
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cebu 6th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,775,000.00

Progress

Reported complete (DPWH)

Start Date

October 7, 2024

Target End

February 15, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.