Flood Control and Drainage25AC0015

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PARSUA RIVER, BARANGAY MARATODO, MAGSINGAL, ILOCOS SUR

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PARSUA RIVER, BARANGAY MARATODO, MAGSINGAL, ILOCOS SUR is a DPWH-tracked public work in Ilocos Sur 1st DEO, Region I. Reported contract value: ₱23,759,960.95. Status: Past target date (DPWH On-Going). Contractor on record: N A IBARRA CONST FOR DIOCLETIANS CONST 24742. Figures trace to dpwh.

Ilocos Sur 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 96%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Parsua River, Barangay Maratodo, Magsingal, Ilocos Sur
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Ilocos Sur 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱23,759,960.95

Progress

Past target date (DPWH On-Going)

Start Date

February 21, 2025

Target End

July 12, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.