Buildings and Facilities19DI0119

CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING SITE DEVELOPMENT (PHASE 2), CALAMBA CITY, LAGUNA

CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING SITE DEVELOPMENT (PHASE 2), CALAMBA CITY, LAGUNA is a DPWH-tracked public work in Laguna 2nd DEO, Region IV-A. Reported contract value: ₱19,799,487.25. Status: Reported complete (DPWH). Contractor on record: GAB-ZION ENT 32555. Figures trace to dpwh.

Laguna 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱19,799,487.25

Progress

Reported complete (DPWH)

Start Date

November 12, 2019

Target End

March 5, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.