FLOOD MANAGEMENT PROGRAM-CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE ALONG ABRA DE ILOG, SITIO KALINYAWAN SECTION, SAN VICENTE, ABRA DE ILOG, OCC. MINDORO is a DPWH-tracked public work in Region IV-B, Region IV-B. Reported contract value: ₱232,634,497.81. Status: Past target date (DPWH On-Going). Contractor on record: ANORE CONST. Figures trace to dpwh.

Region IV-B, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

120 projects · ₱11.6B total · 12 flags

Other projects by this contractor

No sat.

REHABILITATION OF NORTH NAVOTAS PUMPING STATION AND NAVOTAS NAVIGATION GATE (PHASE 3), NAVOTAS CITY (RE-ADVERTISEMENT)

National Capital Region, National Capital Region

2024₱281.2M
Past target date (DPWH On-Going)
No sat.

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PANGALAAN RIVER, BRGY. TIGKAN SECTION (DOWNSTREAM LS), PACKAGE C, NAUJAN, OR. MINDORO

Region IV-B, Region IV-B

2025₱276.1M
Past target date (DPWH On-Going)
No sat.

COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD, BRGY. SAN ANTONIO SECTION, NAUJAN, ORIENTAL MINDORO

Region IV-B, Region IV-B

2025₱276.1M
Past target date (DPWH On-Going)
No sat.

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PANGALAAN RIVER, BRGY. TIGKAN SECTION (LS), PACKAGE B, NAUJAN, OR. MINDORO

Region IV-B, Region IV-B

2025₱276.0M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF LIGAYA-STA. LUCIA COASTAL ROAD (STA. LUCIA SECTION), SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2024₱247.5M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ILVITA RIVERBANK PROTECTION WORKS ALONG AMNAY RIVER (DOWNSTREAM), SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2024₱238.3M
Past target date (DPWH On-Going)
View all 120 projects →

4. Implementation

Contract Amount

₱232,634,497.81

Progress

Past target date (DPWH On-Going)

Start Date

March 2, 2024

Target End

February 24, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.