Construction of Flood Mitigation Structure24NI0058

Construction of Bank Revetment along Bislig River (Pamanlinan Section), Bislig City, Surigao del Sur

Construction of Bank Revetment along Bislig River (Pamanlinan Section), Bislig City, Surigao del Sur is a DPWH-tracked public work in CITY OF BISLIG (SURIGAO DEL SUR), SURIGAO DEL SUR, Region XIII. Reported contract value: ₱96,499,134.76. Status: Reported complete (DPWH). Contractor on record: ME 3 CONST / EVENPAR CONST AND DEVELOPMENT CORP FORMERLY: EVEN PAR CONST CO INC. Figures trace to sumbong.

CITY OF BISLIG (SURIGAO DEL SUR), SURIGAO DEL SUR, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱100,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tinago Flood Control Structure, Brgy. Tinago, Malimono, Surigao del Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-24-0001603

₱1,649,437.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-24-0008052

₱1,417,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-24-0008053

₱131,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱96,499,134.76

Progress

Reported complete (DPWH)

Start Date

April 15, 2024

Target End

May 7, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.