GAA 2025 SSP25OA0016

CONSTRUCTION OF R-10 PUMPING STATION, NAVOTAS CITY

CONSTRUCTION OF R-10 PUMPING STATION, NAVOTAS CITY is a DPWH-tracked public work in Malabon-Navotas DEO, National Capital Region. Reported contract value: ₱33,598,573.85. Status: Past target date (DPWH On-Going). Contractor on record: C T LEONCIO CONST. Figures trace to dpwh.

Malabon-Navotas DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of C-4 Flood Gate (Phase 1), Navotas City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Malabon-Navotas DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

409 projects · ₱21.3B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF BALETE - SAN JOSE DIVERSION ROAD, MATAAS NA KAHOY SECTION (PHASE I), BATANGAS

Region IV-A, Region IV-A

2024₱188.2M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CONSTRUCTION OF LIPA CITY-MATAAS NA KAHOY DIVERSION RD. LEADING TO TAAL CIRCUMFERENTIAL ROAD PHASE 7, BATAN

Batangas 4th DEO, Region IV-A

2024₱187.4M
Past target date (DPWH On-Going)
No sat.

MFO-1 - NAT'L. ROAD NETWORK SERVICES - WIDENING OF DAANG MAHARLIKA (TIAONG SECTION), QUEZON PROV.

Region IV-A, Region IV-A

2016₱178.5M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES -CONSTRUCTION OF MULTI-PURPOSE BLDG. (TRAINING AND INSTRUCTIONAL FACILITY/MEETINGS INCENTIVES CONFERENCES FOR EDUCATION, SPORTS BUILDING (MICES) AND PRIMARY

Albay 2nd DEO, Region V

2024₱169.8M
Past target date (DPWH On-Going)
No sat.

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURE, STO. NINO RIVER WATERWAYS ALONG ARAMAYWAN-BERONG-PTO. PRINCESA ROAD, PALAWAN

Region IV-B, Region IV-B

2025₱161.8M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION PROGRAM- REHAB./RECONST. OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE- SECONDARY ROADS, PUERO PRINCESANORTH ROAD, STA. 215+005-STA. 215+365, TAYTAY, PALAWAN

Region IV-B, Region IV-B

2023₱160.2M
Reported complete (DPWH)
View all 409 projects →

4. Implementation

Contract Amount

₱33,598,573.85

Progress

Past target date (DPWH On-Going)

Start Date

February 20, 2025

Target End

November 16, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.