Buildings and Facilities25NF0070

CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY POBLACION 10, DAPA, SURIGAO DEL NORTE

CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY POBLACION 10, DAPA, SURIGAO DEL NORTE is a DPWH-tracked public work in Surigao del Norte 1st DEO, Region XIII. Reported contract value: ₱4,929,971.26. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: JZL BUILDERS. Figures trace to dpwh.

Surigao del Norte 1st DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure Purok 2, Brgy. Urbiztondo, Claver, Surigao del Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Surigao del Norte 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

81 projects · ₱732.4M total · 0 flags

4. Implementation

Contract Amount

₱4,929,971.26

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 28, 2025

Target End

November 22, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.