Roads23ED0003

PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD K0053+511 - K0054+231.5, SOCORRO, ORIENTAL MINDORO

PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD K0053+511 - K0054+231.5, SOCORRO, ORIENTAL MINDORO is a DPWH-tracked public work in Mindoro Oriental DEO, Region IV-B. Reported contract value: ₱18,645,263.25. Status: Reported complete (DPWH). Contractor on record: SIXTEEN ENT-CALAPAN BRANCH. Figures trace to dpwh.

Mindoro Oriental DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bucayao Flood Control Structure along Barangay Buhuan, Sta. 0 + 000 - Sta. 0 + 200, Calapan City, Oriental Mindoro
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Mindoro Oriental DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

76 projects · ₱2.7B total · 0 flags

Other projects by this contractor

No sat.

ROAD WIDENING OF CALAPAN SOUTH ROAD, KO064+(-780)-KO064+(-320); KO064+(-200)-KO064+328; KO064+456-KO064+638; KO064+822-KO066+680; KO066+868-KO069+053; KO069+356-KO071+160; KO071+273-KO072+128; KO072+241-KO072+445; KO072+628-KO073+687; KO073+794-KO074+640,

Region IV-B, Region IV-B

2018₱204.4M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM- CONST. OF MISSING LINKS/NEW ROADS- BULALACAO-SAN JOSE ROAD (BULALACAO SECTION), ORIENTAL MINDORO

Region IV-B, Region IV-B

2023₱135.1M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MISSING LINKS/NEW ROADS BULALACAO-SAN JOSE ROAD (BULALACAO SECTION), STA. 0+000-STA. 0+044.60; STA. 0+105.40-STA. 1+302; STA. 0+066.60-STA. 0+105.40, ORIENTAL MINDORO

Region IV-B, Region IV-B

2021₱96.5M
Reported complete (DPWH)
No sat.

ROAD WIDENING OF SECONDARY ROADS, CSR (K0094+160 - K0094+191, K0094+200 - K0096+968), BANSUD, ORIENTAL MINDORO

Southern Mindoro DEO, Region IV-B

2018₱96.4M
Reported complete (DPWH)
No sat.

WIDENING OF CALAPAN SOUTH ROAD, SECT. 1-KO085+938-KO086+336; SECT. 2-KO086+657-KO086+846; SECT. 3-KO086+887-KO087+364; SECT. 4-KO087+861-KO088+690; SECT. 5-KO089+171-KO089+764; SECT. 6-KO090+287-KO090+390; SECT. 7-KO090+803-KO091+127; SECT. 8-KO091+578-KO

Southern Mindoro DEO, Region IV-B

2017₱93.6M
Reported complete (DPWH)
No sat.

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG CALAPAN SOUTH ROAD, K0103+632 - K0104+224, K0124+976 - K0126+000, K0127+000 - K0127+400, K0127+560 - K0130+000), BONGABONG, ORIENTAL MINDORO

Southern Mindoro DEO, Region IV-B

2018₱92.4M
Reported complete (DPWH)
View all 76 projects →

4. Implementation

Contract Amount

₱18,645,263.25

Progress

Reported complete (DPWH)

Start Date

March 29, 2023

Target End

July 19, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.