Flood Control and Drainage25CK0079

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG RIO CHICO RIVER, PHASE IV, BARANGAY MATAYUMTAYUM, LA PAZ, TARLAC

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG RIO CHICO RIVER, PHASE IV, BARANGAY MATAYUMTAYUM, LA PAZ, TARLAC is a DPWH-tracked public work in Tarlac 2nd DEO, Region III. Reported contract value: ₱93,058,799.99. Status: Past target date (DPWH On-Going). Contractor on record: A C SOLIVEN CONST. Figures trace to dpwh.

Tarlac 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure (Phase III), La Paz, Tarlac
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Tarlac 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱93,058,799.99

Progress

Past target date (DPWH On-Going)

Start Date

May 20, 2025

Target End

November 19, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.