GAA 2025 SSP25HJ0141

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP)-EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES-CONSTRUCTION OF EVACUATION CENTER/ COVERED COURT, SITIO BANBAN, BARANGAY GUBA, VALLEHERMOSO, NEGROS ORIENTAL

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP)-EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES-CONSTRUCTION OF EVACUATION CENTER/ COVERED COURT, SITIO BANBAN, BARANGAY GUBA, VALLEHERMOSO, NEGROS ORIENTAL is a DPWH-tracked public work in Negros Oriental 1st DEO, Negros Island Region. Reported contract value: ₱4,934,044.15. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: AGB CONST AND SUPPLY. Figures trace to dpwh.

Negros Oriental 1st DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱17,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Tinaogan, Bindoy, Negros Oriental
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Negros Oriental 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,934,044.15

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

June 5, 2025

Target End

October 22, 2025

5. Audit